Client: Sydney Trains
Duration: 2 years
Location: Central Station, Sydney, NSW
Complex, possession-based metro construction in one of Sydney’s busiest live rail environments
- ~90% possession-based scope, requiring precision logistics to deliver materials and plant to live underground platforms -primarily through midweek night-shift windows
- 29 track possessions delivered over a two-year period with zero delays to passenger services, across one of Sydney’s highest-frequency rail corridors
- Rapid mobilisation in response to a major change event -Olympic Tunnel decommissioning works commenced within five days of instruction to meet critical stakeholder and program constraints
- 24/7 delivery over five weeks to complete the Olympic Tunnel scope and successfully execute two back-to-back possession weekends across different platforms
- Demonstrated capability to absorb scope complexity and program pressure in a live metro environment, maintaining safety, quality and client confidence throughout