Client: John Holland, Laing O’Rourke, JV
Location: Sydenham Station, Sydney, NSW
Active railway corridor works for Sydney Metro City & Southwest
- Construction of four 190m (4m wide, 2m high) base slabs and FRP backfill within an active railway corridor for Sydney Metro City & Southwest
- Multi-staged construction to mitigate twice-daily tidal flooding: temporary dams built to redirect Cooks River tidal water before demolition and reconstruction of final two culverts
- Extensive acid sulphate soil and onsite asbestos remediation to geotechnical and EPA requirements; innovative suspension of live 132 and 133kV cables during excavation
- Temporary post-and-panel walls with 12m I-beam maintained a four-lane road within 500mm of excavation throughout —zero diversions required
- Eight concurrent work crews managed within a severely constrained site; programme recovered through extended hours and in-house high-demand plant mobilisation